  • Lynch Basement LED Low Voltage Pot Lighting Installed

    By Rick on June 20, 2017 in Basements
    0
    0

    I have installed the low voltage LEd lighting in the ceiling in the basement. The floor is scraped clean of droppings from the taping process. I have swept everything ready for the installation of the laminate flooring tomorrow.

    Keep Reading
  • Lynch Basement Tape & Prime Completed

    By Rick on June 15, 2017 in Basements
    0
    0

    Now that the taping and prime painting is complete I will be installing the low voltage LED lighting. Once the ceiling finish paint is complete I will install the  air diffusers.

    Keep Reading
  • Lynch Basement Drywall Installed

    By Rick on June 10, 2017 in Basements
    0
    0

    The drywall installation is complete and after cleaning up and taking all the cutoffs to the dump the taping will begin.

    Keep Reading
  • Lynch Basement Spray Insulation

    By Rick on June 6, 2017 in Basements
    0
    0

    Once again the guys have done a nice neat job of spraying the insulation in the basement 2×4 framed walls and joist headers. I have framed an opening in the feature wall for an electric fireplace which I will install later. I have installed cement board on the feature wall so I can install the stone. Some will attach the

    Keep Reading
  • Lynch Basement Ready For Spray Insulation

    By Rick on June 1, 2017 in Basements
    0
    0

    This Brooklin basement is ready for spray insulation. All framing of walls and bulkheads are complete. The rough-in for plumbing and electrical are complete. The HVAC has been redesigned and makes the finish look better already. The 3 wall cracks that were discovered after removing the wrap insulation have been repaired and are complete. I am ahead of schedule so

    Keep Reading